Experiment · Glasgow

What might hockey at the OVO Hydro look like?

A basic, sightline-oriented Blender model built to explore Glasgow Clan games at the Hydro on 30–31 December 2026—and whether raising the ice materially changes views from behind the goals and around the bowl.

Blender viewport overview of the OVO Hydro seating bowl surrounding the modelled ice rink
The Blender model created for this experiment, including the reconstructed seating bowl, regulation rink and seat-level sightline cameras.

This is a visualisation, not venue CAD. Dimensions and elevations were inferred from public seating plans, seat manifests and photographs. The images are intended to compare plausible sightlines, not to promise the view from a purchased ticket.

An end-zone view at the Delta Center where the near end of the ice is hidden below the seating bowl
Delta Center illustrates the same geometry challenge: from some basketball-bowl seats, the near goal and a substantial part of the ice can fall below the spectator's sightline.

Why build this model?

I was wondering what the implications of putting a 60-metre-long ice rink into the Hydro's 71-metre-wide lowered arena floor might be, so I decided to attempt to build a 3D model. Concert floor seats do not introduce boards, safety glass or a near goal; an ice rink does. The experiment lets us explore that unusual geometry, see how the event might feel from around the bowl, and compare what happens if the complete rink is raised by 1.5 or 3 metres.

A useful comparison from Utah

The Utah Mammoth have not moved to a new arena. They remain at the Delta Center, a venue originally designed around the Utah Jazz, while it undergoes a multi-year rebuild specifically intended to make basketball and hockey sightlines work in the same bowl.

  • 2024–25: only 11,131 seats had a full view of the ice; roughly 5,000 seats—mostly in the upper bowl—could see only one goal.
  • Summer 2025: the arena floor was raised two feet, the bowl was lengthened by about 12 feet at each end, and custom retractable risers were installed. Every lower-bowl seat then had a full hockey view for 2025–26.
  • 2025–26: the remaining sightline work was above them. The team reportedly sold about 4,000 discounted upper-deck seats with an obstructed or single-goal view.
  • Summer 2026: the upper-north end is being rebuilt as steep, terrace-style seating so spectators can see the near goal.
  • 2027: major work is planned for the south end using a dynamic slope from the floor upward. SEG's stated end point is full hockey and basketball sightlines from every seat once both ends are complete.

How the model was built

The model was iterated by comparing independent forms of evidence rather than trying to reproduce one photograph.

  1. Established the scale. The clear arena floor was treated as approximately 71 metres in diameter and the ice as a 60 × 30 metre rink.
  2. Reconstructed the seating. Section and row capacities came from seat manifests; numbered-seat patterns helped locate aisles, partial rows and paired-section vomitories.
  3. Estimated the bowl geometry. Overhead plans, level diagrams, rake-angle images and venue photographs informed section angles, tier rises, hospitality levels, exits, rails and the open end of the bowl.
  4. Calibrated against real viewpoints. Sixteen selected A View From My Seat photographs were mapped to approximate seat-level cameras. Repeated differences across several views drove model changes.
  5. Changed one hockey variable. The complete rink assembly—ice, boards, glass, goals and benches—was rendered at 0, 1.5 and 3 metres.

An extraordinary engineering challenge

What would it take to raise the ice three metres?

A three-metre rise seems extremely unlikely—but it would be an incredible feat of temporary engineering if it did happen. The render makes the change look like a simple slider; inside the building it would mean constructing something closer to a temporary two-storey structure than a concert stage. These figures illustrate the scale rather than proposing a design or describing the event's actual installation.

2,275 m²Indicative 65 × 35 m working deck
3 mNearly one storey above the arena floor
50–70 tIce alone at roughly 30–40 mm thickness
25–30 mVehicle ramp at a steep 12–10% gradient

A ground-supported building inside the arena

A regulation 60 × 30 m ice sheet is 1,800 m² before adding boards, benches, penalty boxes and working clearance. Raising an indicative 65 × 35 m footprint would require a level, laterally stable structure capable of carrying:

  • the rink tray, insulation, refrigeration mat and pipework;
  • roughly 50–70 tonnes of ice, depending on thickness;
  • boards, safety glass, benches, players and officials;
  • maintenance loads, potentially including an ice resurfacer;
  • and the considerable weight of the deck structure itself.

The Hydro publishes a 60-tonne roof-rigging capacity over a 51 m grid. A deck of this size and mass would therefore almost certainly need to be ground-supported, subject to the Level 0 slab's certified loading and a specialist temporary-works design.

The resurfacer has to reach the ice

A three-metre rise needs about 25 m of ramp even at a relatively steep 12% gradient, or 30 m at 10%. That ramp must fit somewhere without compromising circulation. Alternatives—a vehicle lift, scissor platform or removable deck section—are themselves substantial engineered systems.

The same design must safely resolve:

  • player, official and equipment routes;
  • stretcher, first-aid and emergency access;
  • accessible routes wherever the raised level is occupied;
  • board gates, refrigeration services and drainage;
  • fire strategy, evacuation, barriers and the usable space below.

Delivering all of that for a short run of games would be a remarkable undertaking. The three-metre render is therefore best viewed as an intentionally ambitious upper bound: useful for showing how elevation changes sightlines, rather than a prediction of the event build.

A plausible expectation is a more practical combination: a modest ice rise designed to improve the amount of ice visible from the majority of seats, thoughtful rink positioning and large screens that help everyone follow the action. At this scale even a perfectly visible puck will look tiny from some seats, so the spectacle is also about letting a huge crowd soak up the atmosphere while the screens keep them close to the play. Glasgow Clan's allocation of centre season-ticket holders to Tier 1 and corner/behind-net holders to Tier 2 suggests that hockey-specific seating decisions have already been made. This remains inference—the installation design has not been published. Sources: Hydro dimensions and technical limits, confirmed event details, and Glasgow Clan ticket-tier information.

Important limitations

The Hydro's roof, event rigging, video screens, crowds and detailed seat furniture are deliberately omitted or simplified. Temporary staging differs between source photographs. Phone focal length, crop and camera height also vary. This experiment is most useful for comparing the relative effect of rink elevation from the same modelled seat.

Data verified to the end of the 2025/26 season, last checked 2026-09-15 21:29 UTC.